As of March 6th, 2002
a. Tasks completed to date
b. Comparison of tasks completed to date
vs. their
annual plan that was submitted
in December
The issues of the official
certification I
listed are now being discussed
as a part of
FSG's official certification.
Our certification policy/procedure
will follow
the FSG/OpenGroup's policy/procedure.
(Need to confirm if the program
schedule also
should match to the
FSG/LSB's one exactly.)
c. Next steps
i. any changes to annual
plan
ii. area's that they need
help
a) Review for the FSG Certification
Policy documents
b) Need members to review
the documents for li18nux
official
certification program
c) Create a system of sign-up
d. other
Current status of the pilot program.
a) Distribution 2
- Conformance
test done by testsuite group
- Approved
by certification group and chairman
- in contract/license
agreement phase w/FSG
b) Distribution 3
- in in-house
testing phase